Filters
Question type

Study Flashcards

There are four activities on the critical path Coincidentally,their standard deviations are all equal to 4 The standard deviation of the critical path is therefore equal to:


A) 2 days
B) 4 days
C) 8 days
D) 16 days
E) 64 days

F) B) and D)
G) C) and E)

Correct Answer

verifed

verified

What is the estimated standard deviation in the time for activity E?


A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

C

What is the estimated mean time for project completion?


A) 100 days
B) 140 days
C) 199 days
D) 200 days
E) 440 days

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

D

In a project network the critical path is the sequence of activities which has:


A) the most activities
B) the fewest activities
C) the most events
D) the longest time
E) the greatest variance

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

-What is the probability that the critical path will be completed within 200 days?


A) 0 8413
B) 0 9544
C) 0 9772
D) 0 9974
E) 0 9987

F) B) and C)
G) C) and D)

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity slack

A) True
B) False

Correct Answer

verifed

verified

The CPM method provides an excellent procedure for evaluating time-cost tradeoffs

A) True
B) False

Correct Answer

verifed

verified

Given this information about activity H: ES = 10,EF = 15,LS = 16,and LF = 21,we can determine that the amount of slack associated with the activity is:


A) 0
B) 1
C) 5
D) 6
E) 11

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

When finding the approximate probability of project duration,it is necessary to know which of the following?


A) The mean and variance of each activity
B) The mean of each activity on the critical path
C) The standard deviation of only the activities on the critical path
D) Each activity's probability of completion
E) The distribution of activity times

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

-What is the estimated standard deviation in the time for activity E?


A) 1 days
B) 2 days
C) 3 days
D) 4 days
E) 5 days

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Project managers must often function in an environment that is beset with uncertainties

A) True
B) False

Correct Answer

verifed

verified

The project management strategy of injecting additional resources in order to reduce the length of the project is called:


A) expediting
B) rushing
C) panicking
D) crashing
E) None of the above

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17 Its slack is:


A) 0
B) 1
C) 4
D) 5
E) 9

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

An important assumption in PERT calculations is:


A) activity durations are normally distributed
B) activity durations are independent
C) a computer will be available to do the calculations
D) a and b only
E) a and c only

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

The slack of any activity is the amount of time that the activity can be delayed without delaying the completion of the project

A) True
B) False

Correct Answer

verifed

verified

The standard deviation of a path is computed as:


A) the sum of the standard deviations of all activities on the path
B) the square root of the sum of the standard deviations of all activities on the path
C) the sum of the variances of all activities on the path
D) the square root of the sum of the variances of all activities on the path
E) None of the above

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path

A) True
B) False

Correct Answer

verifed

verified

In an Activity-On-Node project network,the nodes are used to separate an activity from each of its immediate predecessors

A) True
B) False

Correct Answer

verifed

verified

In project network analysis,slack refers to the difference between:


A) observed and predicted times
B) optimistic and pessimistic times
C) latest finish and latest start times
D) earliest finish and earliest start times
E) latest start and earliest start times

F) A) and C)
G) C) and E)

Correct Answer

verifed

verified

E

An activity has an optimistic time estimate of three days,a most likely time estimate of eight days,and a pessimistic time estimate of ten days The expected duration of this activity is:


A) 7 0 days
B) 7 5 days
C) 8 0 days
D) 8 5 days
E) 10 0 days

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

Showing 1 - 20 of 92

Related Exams

Show Answer