Fred's Fabrication has the following aggregate demand requirements and other data for the upcoming four quarters. Fred's Fabrication has the following aggregate demand requirements and other data for the upcoming four quarters.    Which of the following production plans is better: Plan A-chase demand by hiring and layoffs;Plan B-pure level strategy,or Plan C-700 level with the remainder by subcontracting? Which of the following production plans is better: Plan A-chase demand by hiring and layoffs;Plan B-pure level strategy,or Plan C-700 level with the remainder by subcontracting?

Correct Answer

verifed

verified

Plan A has cost of $378,000,plan B has c...

View Answer

Which of the following aggregate planning strategies is a capacity option?


A) influencing demand by changing price
B) counterseasonal product mixing
C) influencing demand by extending lead times
D) changing inventory levels
E) influencing demand by back ordering

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

Industries in which revenue management techniques are easiest to apply are those where:


A) use tends to be predictable,and pricing tends to be fixed.
B) use tends to be predictable,and pricing tends to be variable.
C) use tends to be uncertain,and pricing tends to be fixed.
D) use tends to be uncertain,and pricing tends to be variable.
E) All of the above,i.e. ,there is no difference.

F) A) and D)
G) All of the above

Correct Answer

verifed

verified

Which of the following aggregate planning options attempts to manipulate product or service demand?


A) inventories
B) part-time workers
C) subcontracting
D) overtime/idle time
E) price cuts

F) B) and D)
G) A) and C)

Correct Answer

verifed

verified

An aggregate plan satisfies forecast demand by potentially adjusting all EXCEPT which of the following?


A) production rates
B) labor levels
C) inventory levels
D) overtime work
E) facility capacity

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

Which of these is among the demand options of aggregate planning?


A) subcontracting
B) back-ordering during high-demand periods
C) changing inventory levels
D) varying workforce size
E) varying production rates through overtime or idle time

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

What four things are needed to develop an aggregate plan?

Correct Answer

verifed

verified

(1)a logical overall unit for measuring ...

View Answer

In aggregate planning,the amount of overtime and the size of the work force are both adjustable elements of capacity.

A) True
B) False

Correct Answer

verifed

verified

Under which of the following do planning tasks associated with job assignments,ordering,job scheduling,and dispatching typically fall?


A) short-range plans
B) intermediate-range plans
C) long-range plans
D) mission-related planning
E) strategic planning

F) C) and E)
G) None of the above

Correct Answer

verifed

verified

The ________ strategy sets production equal to forecasted demand.

Correct Answer

verifed

verified

A professional services firm is investigating revenue management as a means of taking advantage of unused capacity.Analysts for this firm estimate a demand curve for the firm's service,which is sold by the hour.Points on this demand curve include 9000 hours at the current rate of $60 per hour,9500 hours at $55,10,000 hours at $50,and 10,500 hours at $45.Based on this demand curve,what price point would be best for the firm,if its objective is maximum revenue?

Correct Answer

verifed

verified

The yields of these price points are as ...

View Answer

A hotel room that goes unrented,a dental appointment that no patient booked,and an airline seat that went unsold,are all examples of ________ in services.

Correct Answer

verifed

verified

perishable...

View Answer

The use of part-time workers as an aggregate planning option may be less costly than using full-time workers,but it may also reduce quality levels.

A) True
B) False

Correct Answer

verifed

verified

What is a disadvantage common to the following two strategies: (1)varying inventory levels and (2)back ordering during periods of high demand?

Correct Answer

verifed

verified

Shortages or backord...

View Answer

Because service firms do not inventory their output,a pure chase strategy is not appropriate.

A) True
B) False

Correct Answer

verifed

verified

Describe the advantages and limitations of the transportation method for aggregate planning.

Correct Answer

verifed

verified

Advantages include that it provides an o...

View Answer

Showing 101 - 116 of 116